Agile Software Development
Iterative delivery of custom applications with users involved throughout.
What this covers
Custom software is warranted when an agency's process is genuinely distinct or when commercial products do not fit. HQT builds custom applications using agile practices adapted to public-sector constraints, such as fixed budgets and formal acceptance.
Typical activities
- Discovery with users, including residents where the application is public-facing
- Backlog development and prioritization with the agency product owner
- Two-week iterations with demonstrations of working software
- Automated unit, integration, and end-to-end testing
- Accessibility and security checks within each iteration
- Documentation, training, and handover
What you receive
Working software delivered incrementally, source code in the agency's repository, test suites, deployment pipelines, and user and technical documentation.
Considerations for public agencies
Agile and fixed-price procurement can coexist. We scope releases as fixed-price increments with defined outcomes so that the agency has budget certainty and the team has room to adapt details.
Signals that custom development fits this process
Custom development is proposed more often than it is warranted, so test the case before writing a solicitation. The signals that point toward it are specific:
- The process runs on spreadsheets, a shared mailbox, or a desktop database that one employee understands, which concentrates the risk in that person.
- Every product you evaluated would require changing a step that statute, ordinance, or a court rule holds in place.
- A product vendor has quoted heavy configuration plus custom extensions, which is custom software the agency pays for without owning it.
- Nobody in the office describes the current process the same way twice, so requirements cannot be settled on paper before working software exists.
- A legislative change or grant period forces a usable release before the full scope can be built.
Counter-signals carry the same weight. Where the process is common across jurisdictions, such as permitting, licensing, or work orders, a configured product is usually cheaper across its life. Where no one in the program office can give the work regular time in every iteration, iterative delivery stalls regardless of who builds it.
What a healthy iteration looks like, and a failing one
In a healthy project, each demonstration shows the application running in an environment the agency controls rather than a slide deck or a clickable prototype. Acceptance criteria are written before the iteration starts, in language a program manager can read without a translator. The application is deployable from the early weeks even when it does almost nothing, and defects found in an iteration are fixed inside it rather than parked for later.
Failing projects look different, and the signs show up early:
- Demonstrations assembled from designs rather than running code
- A backlog only the vendor can interpret
- Velocity charts offered in place of features the agency has accepted
- A stabilization period that keeps growing as the deadline approaches
- Integration with other systems deferred to the last increment
- Test data that does not resemble production data in volume or in messiness
- A product owner who must carry every decision to a body that rarely meets
Any one of these is correctable on its own. Together they mean the agency will not see the true state of the system until it is nearly out of time.
What to put in the solicitation and the contract
- Commits landing in the agency repository throughout each iteration, with agency staff holding access, rather than a code drop at final acceptance
- A definition of done written into the contract, so that complete is a contract term rather than a vendor judgment
- The right to end the engagement at an increment boundary and keep everything produced to that point, including code, tests, pipelines, and environment definitions
- Named key personnel, with substitution only on written approval
- Deployment into an agency-controlled environment by a stated iteration, so operations and security staff meet the real system early
- A software bill of materials for each release and disclosure of open source license terms
- The accessibility standard named explicitly, chosen against the federal and state rules that apply to your entity rather than left to the vendor to select
Obligations run both ways. The agency owes a product owner with decision authority, subject matter experts on a schedule, representative test data, environment and identity access granted early, and a security review booked at kickoff instead of after the last increment.
Judging the result after the first release
Record a baseline before development starts, or there is nothing to compare the new application against. Useful program measures include the share of transactions completed without staff intervention, elapsed time from submission to decision, the rate of submissions returned for correction, call and counter volume, and staff hours spent on manual steps. Useful delivery measures include lead time from commit to production, the share of changes that require a fix afterward, and defects that reach users.
The measure that settles the question arrives after handover: what it takes in time and cost to make the first significant change without the original team. An application only its builders can change has traded one dependency for another.
Working with HQT on this
HQT scopes this kind of work as a fixed-price or time-and-materials engagement with a written statement of work, named staff, and a defined acceptance process. We are candid about what we can take on and prefer a well-run project to an oversized one. Contact us to discuss a requirement, a draft scope, or an upcoming solicitation.
Frequently asked questions
Who owns the source code when a vendor builds a custom application for our agency?
Ownership is whatever the contract says, so state it rather than assume it. Require that the agency own the custom developed code and that commits land in an agency repository during the work, with tests, pipelines, and documentation delivered alongside it. Third party and open source components keep their own licenses, so ask for a software bill of materials and the license terms for each release. If federal funds pay for part of the system, read the award conditions, because federal grant terms can affect ownership and the license the federal government receives.
How much agency staff time does iterative custom development actually require?
It needs a product owner from the program office who can decide and who is available in every iteration, not only at milestones. Subject matter experts are needed for discovery, for reviewing working software at each demonstration, and for acceptance testing. IT staff are needed for environment access, identity integration, and the security review. An agency that cannot free this time should expect either slower delivery or a system built on the vendor's assumptions about how the work is done.
Do custom applications built for state and local government have to meet accessibility standards?
State and local government web content and mobile applications fall under Title II of the ADA, and the Department of Justice rule implementing it adopts WCAG 2.1 Level AA as the technical standard, with compliance dates that depend on the size of the entity. Many states and larger local governments also have their own accessibility statutes and policies, which can be stricter. Confirm with counsel which standard and date apply to your agency, then name that standard in the contract so conformance is part of acceptance rather than a remediation project after launch.
What happens if the budget runs out before the whole backlog is built?
That risk is the reason to order the backlog by value and to decide in advance which set of functions constitutes a releasable service. If every increment ends with working software deployed to an agency environment, stopping early leaves a system staff can use rather than a half finished build. The contract should let the agency stop at an increment boundary and keep everything produced to that point, so an exhausted budget ends the engagement without stranding the asset.
How do we avoid depending on the vendor that built the application?
Treat handover as something to test rather than something to promise. Before final acceptance, have agency staff or a second vendor clone the repository, build the application, run the test suite, and deploy to a non production environment without help from the delivery team. Ask for the business rules documented in plain language next to the code, since those rules are the hardest part to recover later. If the build depends on tooling, credentials, or environments only the vendor controls, fix that before the team leaves.