User acceptance testing before a government system goes live
How agency staff plan and run user acceptance testing: scenario-based test scripts, tester recruitment, defect severity, and formal sign-off.
When a vendor delivers a configured system, someone at the agency has to decide whether it is fit to run the program. That decision is user acceptance testing, and it is not the vendor's job. The vendor tests that the software works the way it was designed. The agency tests whether that design does the work the agency actually has to do, using the records and exceptions that appear in a normal week at the counter.
UAT is also the last point at which the agency holds real leverage. After go-live and final payment, defects become change requests with a price attached.
What UAT covers, and what it does not
Vendors run unit, system, integration, performance, and security testing before handover. UAT answers a different question: can this office do its job in this system. Several things get folded into UAT without being planned for. Give each its own track and its own testers:
- Functional acceptance. Business processes start to finish, performed in the roles that perform them.
- Data conversion review. Sampled records and control totals compared against the legacy source.
- Interfaces. Traffic in both directions with every connected system, including failure handling.
- Roles and permissions. Each role sees and edits only what policy allows.
- Notices, forms, and reports. Anything residents, courts, or oversight bodies receive, checked against the current template.
- Accessibility. Screens checked against the standard the agency must meet. Requirements vary by jurisdiction and change, so confirm the applicable standard with counsel.
Write test scripts from business scenarios, not feature lists
A script derived from the requirements matrix confirms that a button exists. A script derived from a real case exercises the system the way work arrives. Pull scenarios from files the office handled last quarter: an application submitted incomplete, withdrawn, and resubmitted; a payment reversed after the period closed; an inspection failed twice and appealed.
Each script should state the starting condition, the role performing it, the steps, and the expected result, including what should exist afterward: the notice generated, the ledger entry posted, the audit record retained. Use de-identified historical records where policy permits, and cover month-end close and renewals, not only intake.
Staff it with the people who do the work
Recruit the clerks, inspectors, dispatchers, permit technicians, and accounting staff who will live in the system. Supervisors know the process as documented; front-line staff know it as performed.
- Name testers in writing and protect their time. Testing days are not also normal production days. Arrange backfill.
- Train before testing starts. A tester who cannot navigate the software reports confusion as defects.
- Give testers a stable environment and their own data. Shared environments produce results nobody can reproduce.
- Include the awkward roles. Part-time, field, and counter staff, and anyone using assistive technology.
- Appoint one coordinator. One person schedules sessions, reviews defect write-ups, and is the single channel to the vendor.
Track defects by severity and decide what blocks go-live
Agree on a severity scale before the first cycle and put it in the test plan:
- Critical. A statutory or core function cannot be completed and has no workaround. Always a blocker.
- High. A core function produces an incorrect result, or works only through a manual workaround that will not scale. Normally a blocker.
- Medium. Real but tolerable for a defined period. Deferred only with a named owner and a fix date.
- Low. Cosmetic or convenience issues that go to the backlog.
Expect argument over whether an item is a defect or a change request. Name a triage group with agency and vendor representation, meet on a fixed cadence, and log everything in one tracker both parties can see. Retest fixes inside a full cycle rather than in isolation, because a fix in one module often disturbs another.
Write exit criteria into the plan: no open critical defects, every high defect resolved or covered by a workaround the business owner accepted in writing, every script executed with a pass, conversion accepted, and interfaces verified both ways.
Allow enough calendar time
Plan cycles rather than a single pass. A first cycle surfaces most defects, the vendor fixes and redeploys, a second retests those fixes and the scripts around them, and a third confirms a stable build. Leave working time between cycles, and schedule around fiscal year close, elections, and seasonal peaks. If the go-live date is fixed by statute or a contract expiration, work backwards and protect the test window. Time removed from UAT reappears as post-go-live support.
Sign-off, contract terms, and what to ask the vendor
Acceptance should be a signed document, not an email thread. It should list the scripts executed and their results, open defects with severity and disposition, accepted workarounds and who accepted them, and dated signatures from the business owner and the project sponsor.
- Define acceptance in the contract. The criteria, the length of the test period, the retest cycles included, and the remedy if the system does not pass.
- Tie a payment milestone to written acceptance. A milestone or retainage that survives until sign-off keeps attention on defect resolution.
- Require a test environment refreshed with converted data. Sample data proves little.
- Set response times by severity. Critical and high defects should carry a defined turnaround.
- Read any deemed acceptance clause. Vendors often propose that a system is accepted automatically if the agency does not object within a set period. Negotiate that window and pause it while critical defects are open.
- Ask what happens after go-live. Confirm the warranty period, who fixes production defects, and at what cost.
HQT works with state and local agencies on software delivery and system implementation, including test planning and acceptance support.
Frequently asked questions
Who is responsible for user acceptance testing, the agency or the vendor?
The vendor is responsible for testing that the software works as designed, which includes unit, system, integration, performance, and security testing. The agency is responsible for user acceptance testing, which confirms that the configured system supports the agency's actual business processes. A vendor may supply a test plan, a test environment, training, and defect tracking, but agency staff write the scenarios, execute the scripts, and decide whether to accept.
How long should we allow for UAT on a government system implementation?
Plan for multiple cycles rather than a single pass: an initial cycle that surfaces defects, a retest cycle after the vendor delivers fixes, and a confirmation cycle on a stable build. Allow working time between cycles for the vendor to fix and redeploy, and account for the fact that testers still have day jobs. Schedule around fiscal year close, elections, tax deadlines, and other seasonal peaks that will pull staff away.
What should count as a defect that blocks go-live?
Agree on a severity scale in writing before testing starts. A common approach treats any defect that prevents a statutory or core function with no workaround as a blocker, and treats incorrect results or workarounds that will not scale at production volume as blockers unless the business owner accepts a documented alternative in writing. Cosmetic and convenience issues normally go to a post-go-live backlog with owners and dates.
Should UAT sign-off be tied to a payment milestone?
Tying written acceptance to a milestone payment or to release of retainage is a common practice in public sector software contracts, and it keeps attention on defect resolution when the schedule is under pressure. The contract should state the acceptance criteria, the length of the test period, how many retest cycles are included, and the remedy if the system does not pass. Confirm the specific terms with your purchasing office and counsel before the contract is executed.
What is a deemed acceptance clause and why does it matter?
A deemed acceptance clause states that a deliverable is accepted automatically if the agency does not reject it within a set number of days after delivery. Without adjustment, the clock can run out while staff are still testing or waiting on fixes. Agencies commonly negotiate the length of the window, define what counts as delivery that starts it, and provide that it pauses while critical defects remain open.